whether the installation of the main members at each main node, and the structure of the wall, support, and door openings meet the design requirements of the construction organization;
the strength of the concrete of the engineering structure should meet the requirements of the attached support for its additional load;
the installation of all attachment support points complies with the design requirements. it is strictly forbidden to install unqualified bolts with less attachment attachment connection bolts;
all safety insurance devices have passed the inspection; the settings of power supply, cables and control cabinets are in compliance with the relevant regulations on electricity safety;
the setting and trial operation effect of the synchronization and load control system meet the design requirements; the part of the frame structure using ordinary scaffolding members is up to the required quality;
various safety protection facilities are in place and meet the design requirements; the construction personnel at each post have been implemented;
there should be lightning protection measures in the construction area where the lifting scaffold is attached; necessary fire protection and lighting facilities should be provided for the attachment lifting scaffold;
lifting power equipment works normally; power settings, control equipment, anti-fall devices, etc. should be protected against rain, smashing, and dust.