Safety technical requirements for dismantling bowl-buckle steel pipe scaffolding
Date:2024-05-10
(1) after the scaffolding is used, formulate a dismantling plan.
(2) the demolition sequence is from top to bottom, layer by layer, and the upper and lower floors are not allowed to be demolished at the same time.
(3) the diaphragm braces can only be dismantled when the floor is reached.
(4) the dismantled components should be hoisted with a spreader or handed down manually.
(5)
the dismantled components should be classified and stacked in time for transportation and storage.